projects

  • 23 MW Bikaner, Rajasthan

    Client Name: Fonroche Energy (JNNSM Ph 1 – B II)

    Location: Jodhpur, Rajasthan

    Project Duration: 112 Days

    Technology: Cd-Te Thin film

  • 33 MW Jodhpur, Rajasthan

    Client Name: Mahindra Suryaprakash (JNNSM Ph 1 – B II)

    Location: Jodhpur, Rajasthan

    Project Duration: 128 Days

    Technology: Cd-Te Thin film

  • 5 MW Jodhpur, Rajasthan

    Client Name: Mahindra Solar One (JNNSM Ph 1 – B I)

    Location: Jodhpur, Rajasthan

    Project Duration: 101 Days

    Technology: Poly crystalline with single axis tracker

  • 2.34 MW Hyderabad, AP

    Client Name: Heritage Foods (REC)

    Location: Hyderabad, AP

    Project Duration: 117 Days

    Technology: Poly crystalline

  • 2 MW Lucknow, Uttar Pradesh

    Client Name: Technical Associates (RPSSGP)

    Location: Lucknow, UP

    Project Duration: 71 Days

    Technology: Cd-Te Thin film

  • 2.13 MW Madurai, Tamil Nadu

    Client Name: MM Forgings (REC)

    Location: Madurai, Tamil Nadu

    Project Duration: 88 Days

    Technology: Poly crystalline

  • 6.91 MW Phalodi, Rajasthan

    Client Name: J.K. Lakshmi Cement (REC)

    Location: Phalodi, Rajasthan

    Project Duration: 176 Days

    Technology: Poly crystalline

  • 1.07 MW Madurai, Tamil Nadu

    Client Name: Super Auto Forge (REC)

    Location: Madurai, Tamil Nadu

    Project Duration: 88 Days

    Technology: Poly crystalline

  • 57.5 MW Hulpur, Madhya Pradesh

    Client Name: ReNew Power (State Policy)

    Location: Hulpur, Madhya Pradesh

    Project Duration: 91 Days

    Technology: Cd-Te Thin film

  • 23 MW Mahabubnagar, Telangana

    Client Name: First Solar (State Policy)

    Location: Mahabubnagar, Telangana

    Project Duration: 70 Days

    Technology: Cd-Te Thin Film

  • 12 MW BrightSolar Project

    Client Name: Mahindra DevCo (State Policy)

    Location:

    Project Duration: 65 Days

    Technology: Poly crystalline

  • 44.8 MW Gattu, Telangana- Seasonal Tilt

    Client Name: SunEdison (State Policy)

    Location: Gattu, Telangana

    Project Duration: 85 Days

    Technology: Poly crystalline